Progress is continuing to be made on the Paul E. Joseph Stadium, the Department of Public Works announced Thursday.
DPW contractor – GEC, LLC – has begun plastering and painting the exterior walls of the stadium.

The contractor has also started construction of the interior walls for both concourse levels.

Recently, the construction of the upper concourse floor slab was completed. Steel reinforcement and concrete pours for the bleachers, stairs and risers are still in progress.