WAPA Announces Results of Consecutive Board Meetings

Four new generators at the Randolph Harley Power Plant. (Submitted photo)

The Virgin Islands Water and Power Authority completed two back-to-back board meetings held on June 27 and June 28, the agency announced.

During the June 27 board meeting, several critical decisions and updates were discussed. VIElectron’s solar installation progress was noted, with batteries already installed onsite. Medium-voltage terminations are currently in progress. The Petronella battery lease was brought before the board, but the motion for its approval resulted in a tie and was not carried out, with votes split between board members. The board did approve a motion to engage in direct discussions with VIElectron to address outstanding items, according to the press release,

Additionally, Lorraine Kelly, interim chief financial officer, presented the 14th supplemental bond resolution, which included extending the 2022 Bond Anticipation Notes. This extension allows the July 1 Bond Anticipation Notes to be extended to Aug. 1, facilitating the transition of the outgoing Chief Executive Officer/Executive Director Andy Smith, the press release stated.

Recently, the scope of the Composite Pole Project has been increased to include installation of an additional 2,200 poles territory-wide and a bypass transmission line for Feeder 13.  This amendment request includes the cost associated with the increase in debris associated with the additional scope, as well as the debris associated with the remainder of the original St. Croix Composite Pole Project, the release stated.

This project produces waste such as poles, wires, arrestors and insulators that must be disposed of per EPA RCRA regulations. The board unanimously approved the debris removal motion, which includes a 15 percent increase in the cost of unit items that pertain to off-island shipping and 7 percent for the unit items that do not have an off-island shipping component.  The territory-wide installation of composite poles strengthens our transmission and distribution infrastructure, making it more resilient to natural disasters. Strategic placement, innovative design, efficient material management, and coordinated contractor efforts will ensure durable installations that reduce outages and expedite recovery, minimizing time, effort, and resource expenditures after incidents, i.e., vehicle collisions, overgrown debris, and storms, it said.

The Governing Board approved the first Addendum to Wärtsilä Contract SC-33-20 to not exceed the cost of $10,804,258.00 and a time extension to May 31, 2025, following successful negotiations between the Authority and Wärtsilä. The completion of the additional scopes and time extension were needed for installation of the additional Wärtsilä Phase 2 Engines and Battery Energy Storage System (BESS). Despite unforeseen challenges requiring adjustments to the initial contract, the completion of the Wärtsilä Phase 2 project and BESS will soon provide efficient power generation and stability for the St. Thomas-St. John district, according to the release.

The board also approved two personnel matters in an executive session on June 27. During the June 28 Emergency Board meeting, Ashley Bryan, interim chief operating officer – Electric, was named interim chief executive officer/executive director, it said.

“Our recent board meetings reflect our unwavering commitment to sustainability and community service,” noted Bryan. “We are excited about the progress we are making and the positive impact these initiatives will have on our community.”